Case 01 of 04 · Săliștea Industrial Campus
Owner-Occupier
Industrial Campus
Buy, occupy and expand a 4.5-hectare industrial platform in Alba County, with 4,800 m² usable from day one.
The case
Take over something that already stands
A manufacturer that needs operating space in Romania within twelve months has two options: build it, or take over something that already stands. This asset exists to make the second option credible.

Usable immediately
4,800 m²
Eight separate halls, free of operations
Power available now
217 kW
No new connection required
Expansion headroom
40,000 m²
Unbuilt land inside the fence
What you are actually buying
Not a factory, and not bare land: built envelope, a live medium-voltage connection, a yard engineered for heavy vehicles and four hectares of room, with the groundworks and grid connection already behind you rather than ahead of you. A comparable greenfield project in Alba County typically takes around eighteen months from site acquisition to first production, most of it spent on permitting and utility connection.
Who this case suits
- Light to medium manufacturing, assembly or technical services with a 6–12 month occupancy requirement
- Operations priced out of the Sebeș and Alba Iulia industrial parks, or unable to secure a plot there
- Companies whose growth path needs land banked alongside the first building
Where this case does not work
- Heavy process industry. Approved draw is 241 kVA; above roughly 400 kVA the transformer itself must be changed.
- High-headcount assembly. The commune has 2,155 inhabitants; operations needing 150+ staff must plan transport and housing from the outset.
- Just-in-time automotive supply. The A1 is roughly 17 minutes away. This is not a junction-side logistics location.
- Large-volume wet processes. Wastewater is on septic; mains sewerage would need to be engineered.
Phasing
A phased occupation
Each phase is independently viable: you can stop after any one of them and still hold a working operation.
I Occupy
0–6 months. Take the four 6 m halls for production and the lower halls for storage and maintenance. Use the existing offices. No construction.
II Adapt
3–12 months. Floors, lighting, insulation, fire compartmentation and process services to your specification. Apply for a power increase if the process needs it.
III Build
12–30 months. First purpose-built hall on the development reserve, sized to the demand you have proven rather than the demand you forecast.
IV Consolidate
30 months +. Additional buildings, employee facilities, energy infrastructure or supplier units on the remaining land.
Phases III and IV are subject to planning
Build ratios, permitted height and allowed functions are set by the urbanism certificate, which has not yet been issued. Until then, treat the development reserve as land with evident potential rather than consented capacity.
Documentation
The full case pack
Twelve pages: this case in full, the asset, the electrical documentation, location and access, the transaction process and photography. Released on request, usually within the day.